Sacramento ADU Permits: Fees, Timeline & Process

Pre-approved plans, 60-day review cap, and impact fee waivers under 750 sq ft.

Quick Answer

Sacramento ADUs: $120K–$300K

Permits: $3K–$14K · Updated April 2026

Get Your Exact Estimate

Sacramento ADU Permitting: Overview

Sacramento's ADU permitting process is among the most streamlined in California. Both the City of Sacramento and Sacramento County offer online portals for permit submission, pre-approved ADU plan libraries, and fast review times. Most complete applications are processed in 4–8 weeks, with pre-approved plans sometimes clearing in as little as a few business days.

California's statewide ADU laws provide strong protections for Sacramento homeowners: no minimum lot size, impact fee waivers for units under 750 sq ft, 60-day approval deadlines, and mandatory pre-approved plan programs. The city's ADU Resource Center offers free eligibility checks, plan libraries, and permitting guidance.

Permit Fees Breakdown

Total permitting costs in Sacramento typically range from $3,000–$14,000 depending on ADU type, size, and site conditions.

Fee TypeAmountNotes
Plan Check$1,000–$3,000Based on project valuation
Building Permit$2,000–$6,000Scaled by valuation and scope
Impact Fees (< 750 sf)WaivedCalifornia state law exemption
Impact Fees (750+ sf)$4,000–$15,000Proportional to unit size
School Fees$2–$4/sq ftMay apply at any ADU size
Utility Connections$2,000–$8,000Water, sewer (conversions often exempt)
Inspection FeesIncludedPart of building permit

Fees are estimates based on typical ADU projects. Contact Sacramento permitting for exact quotes. See our full permit fees guide for comparison across cities.

Zoning & Requirements

  • ADUs allowed on most single-family and multifamily lots
  • No minimum lot size (state law overrides local restrictions)
  • Detached ADU max: 1,200 sq ft; Attached max: 50% of primary up to 1,200 sq ft
  • JADU max: 500 sq ft (within existing structure)
  • Height: 16 feet standard; up to 18 feet near transit or above a garage
  • Setbacks: 4 feet rear/side for detached ADUs
  • No parking required near transit
  • Conversion ADUs: no additional setbacks beyond existing footprint

Step-by-Step Permit Process

1

Check eligibility

Use the City of Sacramento ADU Resource Center address lookup tool or Sacramento County's Online Zoning Map to confirm your lot qualifies.

2

Choose plans

Select from Sacramento's pre-approved plan library (free, 10+ options from 460–1,184 sq ft) or commission custom plans. Pre-approved plans get faster review.

3

Submit online

City: Development Services online portal. County: Citizen Access Portal (Accela). Upload site plan, floor plans, Title 24 calcs, structural calculations.

4

Plan review (4–8 weeks)

State law caps review at 60 days for complete applications. Pre-approved plans often clear in 30 days or less.

5

Respond to comments

Address any plan check corrections quickly. A good contractor handles this within days.

6

Pay fees & receive permit

Pay remaining building permit fees, impact fees (if applicable), and utility charges. Permit is issued.

7

Construction & inspections

Schedule through the online portal: footing/foundation, framing, rough plumbing/electrical, insulation, and final. Most are same-day or next-day.

8

Certificate of Occupancy

Pass final inspection to receive your CO.

Key Regulations & Laws

60-Day Shot Clock

California law requires approval or denial within 60 days for complete applications. Pre-approved plans may qualify for 30-day approval.

SB 543 (2025)

Cities must confirm application completeness within 15 business days and cannot introduce new requirements on resubmission.

AB 1332 Pre-Approved Plans

Sacramento offers 10+ pre-approved ADU designs from 460–1,184 sq ft. These are free and have already cleared plan check.

Impact Fee Waiver

ADUs under 750 sq ft are exempt from all development impact fees (school fees may still apply).

AB 1033 (ADU Sales)

Sacramento may adopt this option allowing ADUs to be sold separately through condominium mapping.

HOA Preemption

Under Civil Code Section 4751, HOAs cannot effectively prohibit ADUs on otherwise eligible lots. They can enforce reasonable design standards.

Frequently Asked Questions

How much do ADU permits cost in Sacramento?

Plan check and building permits range from $3,000–$14,000. Impact fees are waived for units under 750 sq ft. Utility connection fees add $2,000–$8,000. Garage conversions are often exempt from new utility connection charges.

How long does ADU permitting take in Sacramento?

Complete applications are capped at 60 days by state law. Pre-approved plans often get approval in 4–6 weeks, sometimes faster. Sacramento's online portal allows real-time tracking.

Does Sacramento have pre-approved ADU plans?

Yes. Both the City and County offer libraries of pre-approved plans (10+ options). These are free, already code-compliant, and significantly speed up review. Sizes range from 460 to 1,184 sq ft.

Do I have to pay impact fees for my ADU?

Not if it's under 750 sq ft — California law waives development impact fees for smaller ADUs. Units 750+ sq ft pay proportional fees. School fees may apply at any size.

TerraLineFree Beta

Track Every Dollar of Your ADU Build

TerraLine is the construction finance cockpit that shows your loan balance, budget burn, and forecast at completion — all on one screen. No more spreadsheets.

Try TerraLine Free

Ready to Start Your ADU Project?

Join hundreds of homeowners who used our guides to navigate their ADU build successfully.

✓ Free comprehensive guide    ✓ Vetted contractor list    ✓ No credit card needed