Payment 1
Before you pay. Get conditional releases from: Your general contractor.
Forms for this payment: Conditional Waiver and Release on Progress Payment (Civil Code § 8132) and Unconditional Waiver and Release on Progress Payment (§ 8134).
Free ADU Tool · California
Paying your builder doesn't mean the plumber, electrician or lumber yard got paid. If they aren't, they can record a mechanics lien on your home. This checklist tracks a signed release from each of them before and after every payment.
Ask your builder for a list of every subcontractor and material supplier on the job. Subcontractors and suppliers who may need to file a lien must send you a Preliminary Notice, so add anyone who sends one and note the date.
Before you pay, get a signed conditional release from everyone that payment will pay. After you pay, get an unconditional release from each of them. Tick each one as it comes in.
0 of 1 payment fully released.
Before you pay. Get conditional releases from: Your general contractor.
Forms for this payment: Conditional Waiver and Release on Progress Payment (Civil Code § 8132) and Unconditional Waiver and Release on Progress Payment (§ 8134).
This browser isn't saving the checklist (private mode or blocked storage). It works, but print it before you leave the page.
General information, not legal advice. This tool explains California rules in plain English. It can't review your contract. For advice about your situation, talk to a California attorney or call the Contractors State License Board (CSLB) at 800-321-2752.
California only. The rules cited here are California law. Oregon, Washington and other states have their own rules, which this tool doesn't check.
A checklist can't confirm that a release is genuine or filled in correctly. Make sure the person who was paid signs it, as CSLB advises.
California requires home improvement contracts to include a Mechanics Lien Warning. Part of it reads:
"Even if you pay your contractor in full, unpaid subcontractors, suppliers, and laborers who helped to improve your property may record mechanics' liens and sue you in court to foreclose the lien. If a court finds the lien is valid, you could be forced to pay twice or have a court officer sell your home to pay the lien."
It happens on ADU jobs. In October 2026 CSLB reported investigating more than 200 complaints against one former ADU builder, alleging unpaid subcontractors as well as abandoned projects and payments made ahead of the work.
Sources: CSLB Contracting for Success; CSLB news release #26-02.
CSLB says a release must substantially follow one of four forms written into the Civil Code to be effective. CSLB hosts a fillable copy of each:
| Form | Civil Code | When to use it |
|---|---|---|
| Conditional Waiver and Release on Progress Payment | § 8132 | Before a progress payment, when the person hasn't been paid yet. It's only effective if they're actually paid. |
| Unconditional Waiver and Release on Progress Payment | § 8134 | After a progress payment, when the person states they've received it. |
| Conditional Waiver and Release on Final Payment | § 8136 | Before the final payment. It's binding only with evidence of payment, such as their endorsement on a check the bank has paid, or their written acknowledgment of payment. |
| Unconditional Waiver and Release on Final Payment | § 8138 | After the final payment, when the person states they've been paid in full. |
Sources: CSLB waiver and release forms; Civil Code §§ 8132–8138.
Sources: CSLB: How to Prevent a Mechanics Lien; Bus. & Prof. Code § 7159.5(a)(6). Make sure each payment is also within the limits with the payment schedule checker.
A conditional release only takes effect once the person signing it is actually paid, so you collect it before you pay. An unconditional release says the person has already been paid, and the form itself warns that it's enforceable against them even if they weren't, so you collect it after you pay.
Yes. CSLB warns that even if you pay your contractor in full, unpaid subcontractors, suppliers and laborers may record a mechanics lien on your property. Paying your contractor, or getting a release from your contractor, doesn't guarantee they paid everyone else.
Yes. Under Business and Professions Code section 7159.5(a)(6), after each payment the contractor has to get you a full, unconditional release for the work paid for if you ask, and you may withhold all further payments until those releases are furnished.
California has four statutory forms in Civil Code sections 8132, 8134, 8136 and 8138: conditional and unconditional releases for progress payments, and conditional and unconditional releases for the final payment. CSLB says a release must substantially follow one of these forms to be effective.
Only in your own browser on this device, if your browser allows it. Nothing is sent to ADU Glossary. Print or save it as a PDF to keep a copy.
Official California sources, checked October 26, 2026. Laws change, so follow the links for the current text.